EGYPT LNG PROJECT (IDKU)



Main Contractor: Vinci Grands Projects and Mitsubishi Heavy Industries. 
Engineer: Bechtel Overseas Corporation. 
Client: Egyptian LNG Co. 
Location: El Beheira Governorate, Egypt. 
Project Duration: 2002-2005. 
Project Facts
  • 2 LNG tanks & ancillary buildings (EPC scope). 
  • The LNG tanks represent one of two existing LNG facilities in Egypt, making this a landmark project for the country. 
  • HAC is one of two contractors, in Egypt, with the equipment and expertise to deliver a project of this kind.
Scope of work
Earthworks & concrete works for piles and walls of 2 LNG storage tanks, each tank has a capacity of 140,000 m3, a diameter of 79 meters, and height of 37 meters.